AMS Renewable Energy

Mallory Solar

PROJECT OVERVIEW
The Mallory site, consisting of an approximately 59.31-acre parcel, is located approximately one mile south of the center of Village of Central Square off of Corporate park Drive in the Town of Hastings, Oswego County, New York. The site houses two individual projects, Mallory I Solar (7.4 MW DC) and Mallory II Solar (7 MW DC).
14,4 MW
Project Capacity (DC)
59,31 Acres
Project Design Area

Solar Project Timeline

2021

OYA begins planning the site with the landowner and local authorities.

2022

OYA is undertaking permitting and environmental surveys.

2023

Construction is expected to start and the project is connected to the grid.

2024

Construction is compleated and ready to start.